Project Schedule

Early 2023

INITIATION

  • Goals and Objectives
  • Project Website
  • Establish Planning Advisory Committee (PAC)
Early 2023

Held Jan. 18, 2023

PAC MEETING #1

Held Jan. 18, 2023

Spring 2023

PHASE 1

  • Inventory
  • Aviation Demand Forecasts
Spring 2023

Held Apr. 5, 2023

Phase 1 PAC Meeting #2
and Workshop

  • Discussion of draft Phase 1 materials
  • Public Information Workshop #1
Held Apr. 5, 2023

Summer 2023

PHASE 2

  • Facility Requirements
  • Airport Development Alternatives
Summer 2023

Held Aug. 8, 2023

Phase 2 PAC Meeting #3
and Workshop

  • Discussion of draft Phase 2 materials
  • Public Information Workshop #2
Held Aug. 8, 2023

Fall 2023

PHASE 3

  • Recommended Master Plan Concept
  • Capital Improvement Program
  • Environmental Review
Fall 2023

Held Dec. 12, 2023

Phase 3 PAC Meeting #4
and Workshop

  • Discussion of draft Phase 3 materials
Held Dec. 12, 2023

Early 2024

DRAFT FINAL MASTER PLAN

Early 2024

Locally approved Feb. 28, 2024

APPROVAL PROCESS

  • Local Approval
  • FAA Approval of ALP
Locally approved Feb. 28, 2024

TBD

FINAL MASTER PLAN

TBD